Tuesday, January 16, 2007

Phase One Complete!

Hellooooooooooooooooo!
Our framers started on Monday Jan. 8th, and completed their job on Friday Jan. 12th, and PASSED INSPECTION! Yippee! Photo's are from the same angle, as the first set, with the framing completed. As you can see, we will have two little "step up" areas to both the right and left of the front door.
Our electrician will start tomorrow, Wednesday (17th) and will hopefully be done by Tuesday.
Our plumbers are going to start Thursday (18th) and will take I think 4 days.
Our heating and cooling guys are planning on coming in next week, as well as our insulator. Drywallers will come in when these people are finished.
We hope to have all of these items competed (and passed inspection) by the end of Jan.
Wish us luck!